I294 Oasis


As part of the Central Tri-State Tollway (I-294) Project, the existing pedestrian bridge that connects Western Springs and Hinsdale is being replaced. The Village, along with the Village of Western Springs, are working together to determine the location of the new bridge. The two proposed locations are: 1) at the existing location at Maple Street/Minneola Street and 2) north of 47th Street at Spring Rock Park and Veeck Park. In either location, the new bridge will meet pedestrian ADA accessibility standards. The Village is considering several factors when determining the replacement bridge location including impacts to adjacent property owners, use of the proposed bridge by Hinsdale residents and community goals. 

Please click here to take the following survey to help us determine the location of the replacement pedestrian bridge.

survey


The Central Tri-State is being reconstructed from Balmoral Avenue to 95th Street to provide congestion relief, reconstruct old infrastructure to meet current and future transportation demand and address regional needs.

Please click here to view the Central Tri-State Tollway (I-294) reconstruction project, concept plan and proposed project timeline.

The Illinois Tollway is reconstructing the Burlington Northern Santa Fe (BNSF) Railway Bridge, which carries the triple-track railroad over the Tri-State Tollway (I-294) between Hinsdale and Western Springs, to accommodate the widening of the Central Tri-State Tollway (I-294).  In 2019, the Tollway will begin work to construct a bypass bridge that will allow for uninterrupted freight and commuter rail operations during bridge reconstruction.  Once the bypass bridge is complete, the main bridge will be rebuilt and lengthened. Work on the BNSF Railway Bridge is scheduled to continue through 2022.

Fiber work on the 4428 BNSF project will begin the week of 9/23 and is expected to be completed in four weeks. The Village of Hinsdale will experience the following impact:

  • Work will include tree removal, three reel trucks with trailers, vac trailer, small excavator and water trailer to be staged in the site access point near Pitchin Kitchen.
  • Up to four trucks and trailers will be parked along the south curb line of Walnut Avenue.
  • Contractor will provide appropriate tree protection measures and site restoration will take place at the conclusion of the project.
  • Tree clearing scheduled to begin next week.
  • Work will be done during daytime hours.
Please click here to view the Burlington Northern Santa Fe (BNSF) Railway Bridge Project, project map and phases.


Tollway Activities Update

9/3/2019 Press Release - Construction scheduled to begin on Burlington Northern Santa Fe (BNSF) railway bridge project on Central Tri-State Tollway (I-294).

Tollway Tree/Brush Removal
Tollway contractors are expected to begin removing trees and brush from the Tollway’s right of way beginning as early as the week of June 24 or as late as July 8, 2019 as part of a plan to relocate fiber within the Tollway’s right of way.  Brush and tree clearing is expected to take as long as a week and will begin at Ogden and work south through Hinsdale.

Property Acquisition
The Tollway has acquired homes located at 423 and 439 Mills.  This is the eighth home of the 10 homes that the Tollway has identified for acquisition as part of the I-294 widening project.  To date the Tollway has acquired 417 Mills, 427 Mills, 439 Mills, 423 Mills, 621 Harding, 645 Harding, 655 Harding and 703 Harding. The Tollway has applied to the Village for demolition permits for 417 Mills, 427 Mills and 645 Harding.  Demolition is expected to occur within the next three weeks.

Click Here to Learn More About the BNSF Railway Bridge Update
Link to the Tollway BNSF project page: https://www.illinoistollway.com/projects/tri-state/bnsf-bridge

Click Here to Learn About The BNSF Bridge Updates

Central Tri-state Tollway Open House

Noisewalls for the Central Tri-State Project

Illinois Tollway Letter to Residents Regarding 417 Mills

Take the Central Tri-State Tollway (I-294) Travel Survey

What You Can Do - Sign up for e-mail updates

What's at Stake?

Seizing the Opportunity - New update 10/25/17

Local Public Discussions

Tollway Timeline

Contact and Information about the Tollway Authority Board

Frequently Asked Questions

Document Archives