A Lamp Construction has been awarded the 2017 Street Resurfacing Project. The scope of work may involve pavement patching, curb and sidewalk repairs, pavement milling, and final pavement resurfacing.  

The contractor will begin the project by mobilizing equipment and materials to 58th St on Monday, April 3, 2017Click here to view the schedule.

The contractor’s progress on the residential portion of this project will determine the starting date in the downtown district.  Per the contract, A Lamp cannot begin downtown activities until July 5, 2017. A Lamp will submit a more detailed downtown schedule in May.

Downtown -
Daytime construction activities will be staged in order to keep one side of the street open.  Parking will be restricted to the open side of the street.  Alternate shopper parking areas will be determined and posted.  

Daytime operation hours will be from 7 AM to 4 PM, while nighttime operation hours will be from 10 PM to 6AM.  Due to the scale of the night activities, full street closures will be required.  Traffic will be detoured around closed sections of street.

Residential -
Daily operations will begin at 7 AM and should be completed by 4 PM. Driveway access will be affected for areas with construction activity.  Access will be restored by the end of each day.  No street parking will be allowed during the scheduled work days listed per street.  To avoid conflicts with construction operations, please have your vehicles out of the driveway prior to 7 AM.   The project is scheduled for completion by mid-August 2017. 

Residents should avoid the construction zones as much as possible.  Daily parking is available on side streets.  If travel through the work zone is necessary, please use extreme caution. 

Thank you for your patience and cooperation. Please contact the Village of Hinsdale Engineering Department at adiaz@villageofhinsdale.org or call 630-789-7029 with any questions or concerns.