How Can We Help You?
Popular Searches:
2016 Roadway and Infrastructure Project
Project Objectives
- Vine Street Reconstruction
- Sewer separation (construction of a storm sewer) on Vine
- Replacing Portland Cement Concrete pavement with hot-mix asphalt pavement
- First Street Reconstruction
- Reuse existing brick
- Addition of Portland Cement Concrete curb & gutter
- Adding a storm sewer to capture sump pump discharges
- Replace existing 4- and 8-inch water mains
7/15/16 North Vine St- Resident Assistance w/ Sod Watering
6/29/16 North Vine St- Sod Watering
6/22/16 North Vine St. Activity Schedule week of June 27th
6/21/16 REVISION Binder Asphalt Paving-North Vine St (North St to Ogden)
6/15/16 Binder Asphalt Paving- North Vine St (North St to Ogden Ave)
6/15/16 Intersection Asphalt Milling: North Vine - E First St
5/25/16: North Vine St-Schedule Update
5/17/16: North Vine St- Pavement Renewal Operations
05/13/16: North Vine St - Resume Pavement Removal Operations
05/13/16: East First St-Concrete Work- REVISED Street access
05/10/16: East First St. - Concrete Work & Road Closure
04/28/16: East First St - Concrete Work
04/21/16: North Vine St.- Resume Storm Sewer Installation
04/21/16: East Fist St.-Road Base Excavation Suspended
04/20/16: East First St. - Road Base Excavation
04/13/16: Water Service Transfer on First Street
04/11/16: Resuming Construction Activity on First Street
03/31/16: Update on Construction Activity on N Vine Street
03/30/16: Resuming Construction Activity on N Vine Street
03/18/16: N. Vine Activity Interruption
03/17/16: Water Main Installation
03/10/16: North Vine Street Storm Sewer Installation
03/09/16: First Street Brick Salvage Operation
03/08/16: Early Start Time Approval
03/07/16: Project Kickoff Notice